New nitrogen plant in the Netherlands was delayed by pandemic
Gasunie analyzes impact of the delay in nitrogen production
Natural gas production at the giant Dutch field Groningen may be temporarily increased because of construction delays at a processing plant for imported fuel.
The new nitrogen installation in Zuidbroek, Netherlands, is behind schedule after pandemic-driven lockdowns delayed delivery of building materials and construction work, Gasunie said in a statement on Tuesday. As a result, Groningen may be called upon for greater volumes of gas to ensure ample domestic supplies at a time when it was expected to begin shutting down.
Groningen is required to shut next year after decades of draining its gas triggered earthquakes, prompting the Dutch government to intervene. The announcement that the field may yield more fuel in coming months could help ease winter-supply concerns that have driven prices to all-time highs.
Source: Bloomberg
Groningen has been a key source of gas for much of Western Europe, as well as the backbone of Dutch sovereign finances, since output commenced in 1963. Imported gas is too rich to flow through the gas networks of the Netherlands and its neighbors, so it requires nitrogen treatment to make it suitable.
The Zuidbroek nitrogen was targeting an April 2022 startup but completion delays “had become a real risk”, Gasunie said in the statement. Two of the three production units are now expected to be ready by the end of June, with the remaining line slated for mid-August.
The decision on whether to pump more gas from Groningen also will hinge on the impact of winter weather on heating demand, according to a Gasunie spokeswoman.
(Adds potential impact on European energy crisis in third paragraph)
Ofgem throws a spanner into GB’s interconnector ambitions – Watt-Logic In March, Ofgem disappointed many by indicating that it is minded to reject all but one of the seven interconnector projects applying for authorisation under […]
Daily Standup Top Stories After Only 15 Years Of Operation, Germany’s First Offshore Wind Farm Being Scrapped March 17, 2025 Stu Turley Germany’s Alpha Ventus offshore wind farm, in operation for 15 years, will be dismantled […]
A BMWK spokeswoman confirmed the signing of the charter agreement to LNG Prime in an emailed statement on Friday. “The FSRU Energos Power has now been sub-chartered to Egypt – the BMWK has successfully signed […]
We use cookies to ensure that we give you the best experience on our website. If you continue to use this site we will assume that you are happy with it.