Venture Global’s CP2 LNG to start mobilization and site preparation

ENB Pub Note: Update from LNGPrime.com below, and I added the summary from the Venture Global Q1 2025 report as we review investment discussions and opportunities.

Venture Global expects to ship 367–389 LNG cargos in 2025, with 145–150 from the Calcasieu Pass facility and 222–239 from the Plaquemines facility. These projections include the 34 and 29 cargos exported from Calcasieu Pass and Plaquemines, respectively, in Q1 2025.
Analysis of Venture Global’s Q1 2025 Earnings Report
The most recent earnings report available is for the first quarter of 2025, released on May 13, 2025. Below is a detailed analysis based on the financial and operational highlights:

Financial Performance

Operational Highlights
Challenges and Market Dynamics
Strategic Positioning
Stock and Analyst Perspectives
Critical Observations

FERC said on May 30 it had granted Venture Global CP2 LNG’s July 2024 request.

“In considering this notice to proceed, we have reviewed CP2 LNG’s implementation plans, and the best management practices described in your application and subsequent filings,” FERC said.

FERC said this letter authorizes only the following activities.

These include mobilization, utility connections and installation of water wells, dewatering and drainage, establishment of temporary access controls, construction of temporary facilities, including access roads and parking areas, installation of erosion control measures, site preparation, and use of existing marine offloading facilities.

In a separate letter, FERC also authorized CP2 LNG to start construction activities for the test pile program for the LNG storage tanks.

FERC recently reaffirmed its previous approval of Venture Global’s CP2 LNG project and the project’s pipeline.

The CP2 LNG plant will be located next to Venture Global’s existing Calcasieu Pass liquefaction plant in Louisiana, which started commercial operations in April.

CP2 is expected to have peak production capacity of up to 28 mtpa.

Venture Global estimates that the total project costs for the CP2 project, including both phases, will range from about $27 billion to $28 billion.

In March, Venture Global announced it had launched the formal FID process for CP2 LNG.

Source: Lngprime.com

We give you energy news and help invest in energy projects too, click here to learn more

Crude Oil, LNG, Jet Fuel price quote

ENB Top News 
ENB
Energy Dashboard
ENB Podcast
ENB Substack

Exit mobile version