BP expects first Tortue gas over next three or four months, CEO says

BP

Asked about the timing of first gas and LNG cargoes from Tortue during BP’s second quarter results call on Wednesday, Auchincloss said that BP continues to make “good progress” on the project.

He noted that the project’s floating production, storage, and offloading (FPSO) unit has arrived at the GTA project off the coasts of Mauritania and Senegal.

Prior to the FPSO, BP said in February that Golar LNG’s FLNG Gimi, which was converted from a 1975-built Moss LNG carrier with a storage capacity of 125,000 cbm, has arrived at the GTA hub.

The FLNG unit is at the heart of the GTA Phase 1 development, operated by BP with partners, Kosmos, PETROSEN, and SMH.

Auchincloss said that BP and its partners are now “hooking together all the equipment, and we’ll have to start to flow gas relatively soon.”

“We obviously need to leak test, make sure everything is okay.. And once we’ve got the leak testing done, then you’ll move into starting the refrigeration units inside the FLNG, and then you can start to build up cargoes,” he said.

“We would look to introduce first gas into the system to start all the pressure testing, etc., over the next three or four months, I think, would be a comfortable place to say,” Auchincloss said.

“So that’s what we can say on Tortue. I’ll just say to the teams in the field who are listening, stay safe guys, no matter what safety is all we care about,” he said.

BP ‘s partner Kosmos said in May that “hookup and commissioning of the FPSO remain on the critical path to first gas, expected in the third quarter of 2024 with first LNG expected in the fourth quarter of 2024.”

Prior to that the project was delayed due to the subsea scope.

With eight processing and production modules, the FPSO will process around 500 million standard cubic feet of gas per day.

The gas supplies will then be transported by pipeline to the FLNG unit at the GTA hub where it will be cryogenically cooled in the vessel’s four liquefaction trains and stored before transfer to LNG carriers.

The project is set to produce around 2.3 million tonnes of LNG per year.

It is expected to produce LNG for more than 20 years, enabling Mauritania and Senegal to become a global LNG hub, BP previously said.

Source: Lngprime.com

Take the Survey at https://survey.energynewsbeat.com/

1031 Exchange E-Book

Crude Oil, LNG, Jet Fuel price quote

ENB Top News 
ENB
Energy Dashboard
ENB Podcast
ENB Substack

About Stu Turley 4195 Articles
Stuart Turley is President and CEO of Sandstone Group, a top energy data, and finance consultancy working with companies all throughout the energy value chain. Sandstone helps both small and large-cap energy companies to develop customized applications and manage data workflows/integration throughout the entire business. With experience implementing enterprise networks, supercomputers, and cellular tower solutions, Sandstone has become a trusted source and advisor.   He is also the Executive Publisher of www.energynewsbeat.com, the best source for 24/7 energy news coverage, and is the Co-Host of the energy news video and Podcast Energy News Beat. Energy should be used to elevate humanity out of poverty. Let's use all forms of energy with the least impact on the environment while being sustainable without printing money. Stu is also a co-host on the 3 Podcasters Walk into A Bar podcast with David Blackmon, and Rey Trevino. Stuart is guided by over 30 years of business management experience, having successfully built and help sell multiple small and medium businesses while consulting for numerous Fortune 500 companies. He holds a B.A in Business Administration from Oklahoma State and an MBA from Oklahoma City University.