Oracle’s $165 Billion Data Center Plan Gets a Gas Pipeline Delay
Oracle’s ambitious $165 billion Project Jupiter data center campus in Doña Ana County, New Mexico—near the U.S.-Mexico border—has hit a low-tech but high-stakes snag. The natural gas pipeline critical to powering it will not be ready on the original timeline. Energy Transfer subsidiary Transwestern Pipeline has delayed the in-service date for its Green Chile Project […]