Indonesia’s Pertamina says that the Jawa-1 LNG-to-power project, which includes the 170,000-cbm Jawa Satu FSRU and a 1.76 GW power plant in the country’s West Java province, is ready to launch full operations.

According to a statement by state-owned Pertamina, the PLTGU Jawa-1 power plant is ready to operate at full capacity after passing a series of tests on March 29.

This is the largest integrated power plant in Southeast Asia equipped with a regasification system, it said.

The project is managed by Jawa Satu Power (JSP), which is owned by a consortium consisting of Pertamina New & Renewable Energy (Pertamina NRE) with a 40 percent ownership, while Japan’s Marubeni and Sojitz own 40 percent and 20 percent respectfully.

Also, Indonesian power producer PLN will take all of the electricity produced by the project as part of a long-term contract.

The plant consists of two units with a capacity of 880 MW each.

According to Pertamina, the second unit has been in commercial operation since December 2023.

By using LNG as a fuel, the resulting greenhouse gas emissions are lower than coal power plants, the firm said.

Pertamina said it expects the project to reduce carbon emissions by 3.3 million tco2e per year.

Back in February 2022, Pertamina said that the Jawa-1 PLTGU power plant had reached the first fire milestone at the first unit.

The firm said at the time that he largest gas-fired power plant in Southeast Asia was expected to “receive a commercial operation date (COD) this semester.”

Pertamina did not provide in the new statement the reasons behind the delay.

The power plant gets LNG from BP’s Tangguh facility in Indonesia’s Papua Barat province via the Jawa Satu FSRU.

In April 2021, the FSRU received its first commissioning cargo.

Moreover, the vessel works for Jawa Satu Regas, a joint venture consisting of Pertamina, Marubeni, Sojitz, and MOL.

MOL operates and maintains the unit with a 300 MMscfd regas capacity.

The FSRU sends regasified LNG to the power plant via some 21 km of gas pipelines located both offshore and onshore.

Source: Lngprime.com

Take the Survey at https://survey.energynewsbeat.com/

1031 Exchange E-Book

ENB Top News 
ENB
Energy Dashboard
ENB Podcast
ENB Substack

 

About Stu Turley 3386 Articles
Stuart Turley is President and CEO of Sandstone Group, a top energy data, and finance consultancy working with companies all throughout the energy value chain. Sandstone helps both small and large-cap energy companies to develop customized applications and manage data workflows/integration throughout the entire business. With experience implementing enterprise networks, supercomputers, and cellular tower solutions, Sandstone has become a trusted source and advisor.   He is also the Executive Publisher of www.energynewsbeat.com, the best source for 24/7 energy news coverage, and is the Co-Host of the energy news video and Podcast Energy News Beat. Energy should be used to elevate humanity out of poverty. Let's use all forms of energy with the least impact on the environment while being sustainable without printing money. Stu is also a co-host on the 3 Podcasters Walk into A Bar podcast with David Blackmon, and Rey Trevino. Stuart is guided by over 30 years of business management experience, having successfully built and help sell multiple small and medium businesses while consulting for numerous Fortune 500 companies. He holds a B.A in Business Administration from Oklahoma State and an MBA from Oklahoma City University.