Petra Diamonds to keep Williamson mine idled until mid-2023

Petra

On November 7, part of the eastern wall of Williamson’s tailing dam collapsed, releasing a total of 12.8 million cubic metres of water and tailings material that flooded nearby areas.

There were no injuries or fatalities and the mine pit was unaffected, Petra said. It added that water and tailings material samples taken by the Tanzanian Government Chemist Laboratory Authority did not find dangerous chemicals and the ones detected were within normal parameters.

Petra, which also operates three diamond mines in South Africa, said its Tanzanian subsidiary, Williamson Diamonds (WDL), has built since an initial 6-metre-high wall to close the breached wall area.

As a precautionary measure, WDL has also put up containment walls upstream and downstream of the New Alamasi water dam, while support for facility’s new wall is under way.

Various diversion trenches are also being constructed to prevent any build-up of water and to enable rainwater to flow into the surrounding rivers and streams, Petra said.

Up to one-year wait

In a preliminary assessment, both Petra’s and independent external specialists concluded that the failure was the result of a subsidence of a portion of the TFS’ East wall measuring around 1.5 metres. This enabled water to crest the wall, initiating the breach.

“The root cause of the subsidence has not been determined and will require a forensic geotechnical investigation to be completed,” Petra said.

“This work will be undertaken by an independent company specializing in tailings dam design and management,” it added.

Cost and timing of the investigation will be available after a detailed scoping process is completed, but the miner said initial estimations point to between six and 12 months.

The company said that, in light of the failure of the existing facility, the design of the new TSF is currently under review, and is expected to be finalized in February 2023.

Petra warned the new TSF will take longer than initially anticipated to become operable. In parallel, an option of repairing and using the existing TSF is also being explored as a long-term solution, but this is subject to the outcome of the geotechnical investigation.

Financial support

Petra, which owns 75% of Williamson, said it was in talks with the government of Tanzania, which owns 25% of the diamond mine, on options for financial support during the production halt.

One of the options proposed by the company is the release and sale of a 71,654 carat diamond parcel seized by Tanzanian authorities in 2017.

At the time, Petra had to halt operations at Williamson, the source of the confiscated diamonds, as local authorities claimed the company was undervaluing its exports, which the miner has denied.

The Williamson mine has been the target of illegal artisanal miners in the past. (Image courtesy of RAID.)

The two parties reached an agreement in December 2021, with the Tanzania government agreeing to release the proceeds of the parcel sale to the company.

Operations at Williamson were halted for months last year due to a decline in diamond prices. During this time, the mine was subject to numerous incidences of illegal mining, and accusations of human rights abuses by security guards trying to keep intruders at bay.

Petra investigated the claims and end up reaching a $6 million settlement.